Facility Needs Report
2016 JCS Facility Needs Report by Hite Associates

An external independent audit of Johnston County Schools facilities conducted by Hite Associates in Greenville showed the most pressing facility needs of the school system. The largest areas of concern and the most immediate needs are as follows:


SCHOOL

PROJECT

ESTIMATED COST

Clayton HS

Demo & Replace Football Bleachers (Identified safety concern by independent contractor)

$205,065

Clayton HS

Multi-purpose building

$500,000

Clayton MS

Roof Replacement

$5,243,000

Cleveland ES

Roof Replacement

$2,621,500

Cooper ES

New 125 Ton Chiller

$133,750

East Clayton ES

Replace chillers and cooling tower (HVAC)

$449,400

Four Oaks ES

Roof Replacement (Butterfly Building)

$531,790

Meadow School

Replace controllers (HVAC)

$240,750

North Johnston HS

Replace Controllers, Hydronic Pipe Insulation & Piping, Gym Equipment. (HVAC)

$920,200

Pine Level ES

Replace Front End & Controllers (HVAC)

$294,250

Princeton M/HS

Replace controls (HVAC)

$374,500

Selma ES

Replace Roof (Buildings 4, 5, 6, 8)

$1,863,699

Selma MS

Roof Replacement

$4,010,895

Selma MS

Replace Chiller(HVAC)

$321,000

Smithfield MS

Roof Replacement

$749,000

Smithfield-Selma HS

Replace Controllers, Hydronic Pipe Insulation, Coiling Issues (HVAC)

$361,125

Smithfield-Selma HS

Roof Replacement

$5,890,885

Smithfield-Selma HS

Multi-purpose building

$500,000

South Johnston HS

Roof Replacement (Main Building)

$5,838,455

South Johnston HS

Facilities Upgrade

$500,000




TOTAL


$31,549,264